Phase I Fence Replacement Project Update

FBCLID 17 has contracted with Johnson Fence for the completion of the Phase I Fence Replacement Project. This project consists of the replacement of approximately 7,800 linear feet of failing concrete panel fence with brick fence. The total cost of the project is approximately $1.1 million. The project work area was primarily located along Chatham Avenue south of New Territory Boulevard, Telfair Avenue west of Addison Avenue and Kempton Avenue south of Telfair Avenue. A layout of the project area is provided below.

The Notice to Proceed on the project was issued to Johnson Fence on September 10, 2020. As of May 5, 2021, the contractor has completed a total of approximately 8,000 linear feet of fence which includes the demolition of the existing fence and installation of brick fence. Johnson Fence is currently completing the final segment of fence replacement on Peatwood Way. Johnson Fence anticipates completion of this final segment by May 11, 2021. A final inspection for the project is also scheduled for Tuesday, May 11, 2021. It is anticipated that the Phase I project will be complete prior to the end of May 2021.